See Completed Projects

Ouzledale Foundry, Barnoldswick - New Industrial Estate

Employment Nursery Units - Cross Hills

St Johns Beaumont School - Old Windsor

Rivermead Leisure Complex -

Windsor Ball Hall - Windsor

Ebor Mill - Howarth

Oak Mount Trade Park - Accrington

Lucas Site - Reedley

Jebel Ali International Airport - Dubai

Khanjra Foods - Blackburn

Former Colne College - Colne

PCT Swindon Clough - Colne

KFC, St Neots - St Neots

Express by Holiday Inn - Sutton in Ashfield

Spirit Business Park - Speke

Dylan Harvey New Business Development - Burnley

DVLA Swansea Phase 6,7 & 8 - Swansea

Vantage Court - Barrowford

Derby Street - Manchester

Goodlass Road - Speke

Ace Centre Market Street - Nelson

Rasool Brothers Housing Ltd - New Housing site for 11 Units, Keighley

Centurian Business Park - Industrial Units with offices

Empire Mill, Liverpool Road, Burnley - Burnley

Hilton Hotel - Coventry

Grove Mills - Keighley

Project: New Housing site for 11 Units, Keighley

Client: Rasool Brothers Housing Ltd

Architectural Design: Paul Waite Associates

Project Manager: Paul Waite Associates

Planning Submission: December 2006 – submitted on line through the planning portal.

Planning Approval: Anticipated March/April 2007

Contractor: To be appointed

Site Start Date: April 2007

Completion Date: April 2009

Contract value: £3.5M

Description: This is a unique housing site for an Asian developer who wants to create an individual site for an Asian market within an established Asian area of Keighley. The design is for 11 modern semi detached housing units having floor areas of between 1,600 sq ft to 2,000 sq ft. Because of its location within an Asian area and modern construction demand for these units is high, with high interest to buy off plan.

The site layout complies with all normal planning requirements, but presented us with many problems as designers, which we had to resolve prior to the planning submission. The problems included:
1. Steeply sloping site resulting in some four storey units and large retaining walls.
2. Surface water attenuation and pumped foul and surface water.
3. Designing a layout within a site of trees subject to TPO’s
4. A site layout that presented challenges in maximising the layout, whilst maintaining separation distances, offsite car parking and internal road layout.

Working drawings will commence in March 2007 and a contract will be negotiated at roundabout the same time.